The short answer
Yes, if the work cuts into a shared wall, such as cutting away a chimney breast, or adds a wall on the boundary or digs close to the neighbour's building. The building owner serves the notice: allow at least two months ahead for the party structure and at least one month for a boundary wall or excavation.
Who serves the notice, and when
The Party Wall etc. Act 1996 sets the duty on the building owner, the person paying for the work rather than the roofer. A notice goes to each adjoining owner in writing before work begins. Neither a builder nor a surveyor serves it by default, and a roofer's job does not stretch to doing it for you.
The lead time depends on the work. Under section 3, notice of work to a party structure has to "be served at least two months before the date on which the proposed work will begin". Under section 1(2), a wall newly built on the line of the boundary, or beside it, needs notice "at least one month before he intends the building work to start". Digging close to the neighbour's building has its own notice, again with a one-month minimum.
A notice that gives the right date and describes the work in plain terms is easier for a neighbour to answer. The Act sets timings and a way of settling a dispute, and it does not call for a roofer's quote to be attached. If you are unsure what to write, a party wall surveyor can advise on the wording.
Building control does not deal with party walls, and a party wall surveyor can advise on them. The two run side by side, because the building regulations look at the structure and the Act looks at the neighbour. Our building regulations guide covers the first.
Roof jobs that may trigger it
Section 2(2)(g) names cutting away from a party wall "any projecting chimney breast, jamb or flue". That is why removing the breast of a chimney on a shared wall is the roof-adjacent job that brings the Act in. Cutting a flashing into a shared wall may count too, so ask a party wall surveyor if the work goes that far.
| Work | Notice |
|---|---|
| Cutting away a chimney breast | At least 2 months |
| New boundary wall | At least 1 month |
| Excavation beside a neighbour | At least 1 month |
A repair that stays inside your own roof slope, clear of any shared wall, does not bring the Act into play in the way a chimney breast does. The position depends on the house, though, so a short check is better than an assumption. Terraced and semi-detached homes share walls, and the line of a roof does not always follow the line of the boundary.
Building Regulations approval is a separate requirement for a chimney breast coming out, whichever wall carries it, so a shared stack brings both sets of rules into play and both need planning for.
What the neighbour can do
After notice has been served, the neighbour has 14 days to reply. Under section 5, an owner who gives no consent in that period is "deemed to have dissented from the notice". GOV.UK puts it plainly: "You cannot assume that no response means they agree to the works." The 14 days are a reply period, not the lead time, which stays at one or two months.
Dissent is not a veto. It leads to the procedure in section 10, where a dispute is settled by an agreed surveyor or by a surveyor for each side. GOV.UK says you must appoint a surveyor if you and your neighbour cannot agree. Written consent is the quicker route, and works may proceed "with the consent in writing of the adjoining owners and of the adjoining occupiers".
Plan your dates around that. A job that needs two months' notice cannot start on the day a quote is accepted, so the scaffold booking and the roofing dates may have to move. Our roofing costs explainer shows how a written total is reached, and the Daylight Roofing home page lists the work we carry out.