The short answer
Only if the scaffold goes on or over the highway. Under section 169 of the Highways Act 1980, scaffolding on the pavement or road needs a scaffold licence from the highway authority, while scaffolding on private land does not. For our jobs, we arrange the licence with our scaffolder.
When a scaffold licence is needed
Section 169 of the Highways Act 1980 says no person shall "erect or retain on or over a highway any scaffolding or other structure which obstructs the highway" without a licence. The words that matter are on or over. A tower on the footway outside a terrace is caught, and so is a scaffold on your own frontage that projects across the footway.
A scaffold wholly inside your boundary is a separate case. Luton Council's page makes the point for its area, saying that no licence is required when the scaffold "is on your private property and does not encroach onto the public highway". The reasoning carries to any address, because the licence follows the highway and not the roof job.
The licence is a Highways Act scaffold licence, and it comes from whichever authority looks after the road concerned. Across most of our area that is the unitary council for the address. In Hertfordshire it is Hertfordshire County Council, and the district or borough council does not issue it. Trunk roads, such as the M1 and the trunk sections of the A5, belong to National Highways.
On Central Bedfordshire's roads the licence is that council's to give, and for each address we work at we arrange the licence with our scaffolder. Where a roof job needs scaffold, the scaffold is part of the written quote's single total.
What each council publishes
Each highway authority sets its own fee and period. The table gives the figure each council publishes on its own page, attributed by name.
| Council | Published fee |
|---|---|
| Luton Council | £205 for up to 28 days, plus a £550 deposit |
| Bedford Borough Council | £178.25 per month or part month (2026) |
| Milton Keynes City Council | £189 up to 1 month, excluding VAT |
| Buckinghamshire Council | £402.78 for 28 days |
| Hertfordshire County Council | £134 for 14 days, £59 each week after |
Some councils say who applies. Luton Council's page states that "for scaffolding the licence is issued to the scaffolding company", and its £550 deposit is refundable once the work is complete and has passed inspection. The application form from Bedford Borough Council says a licence "will normally only be issued to the Company responsible for actually erecting the scaffolding". Buckinghamshire Council says you must be a registered scaffolding company to apply.
Hertfordshire County Council's page adds one more line: "It usually takes 3 weeks to process an application." Each figure belongs to the council named beside it and covers addresses on that council's roads only, so a reader in Luton, for example, looks at the Luton row and nothing else. Milton Keynes City Council's page asks the applicant to take responsibility for applying for the correct licence.
Planning the timing of a licence
A licence takes time, and the council sets how much. Luton Council asks for a minimum of 10 working days, Bedford Borough Council's form allows 10 working days too, and Hertfordshire County Council gives its 3 weeks. A scaffold that needs a licence cannot go up on the morning the roof is due to be stripped, so the roofing date has to wait.
A licence is issued for a period, and the period can be extended. Hertfordshire County Council wants a renewal application five working days or more ahead of expiry, and Luton Council has an extension form. A job that overruns its first licence does not have to come down halfway, provided the extension is arranged in time and the dates are kept under review as the work goes on.
Scaffold is one of the larger items on a roof job, and it sits inside the single written total we give after the survey. Our roofing costs explainer shows what moves a price, and the guide to choosing a roofer lists what to check on any quote, including what it covers. The Daylight Roofing home page lists the work we carry out.