01 Roofs that share a wall
Two houses under one roofline share a party wall, and can share a chimney stack and a valley or parapet gutter too. Work that cuts into the wall, such as taking out a chimney breast, falls under the Party Wall etc. Act 1996. For party-structure work the notice must "be served at least two months before the date on which the proposed work will begin". For a new boundary wall, or excavation close by, the notice period drops to "at least one month before he intends the building work to start".
A neighbour who stays silent for 14 days is "deemed to have dissented from the notice", and that opens the surveyor procedure of section 10, not a veto. Written agreement from the neighbour can also bring the start forward. A party wall surveyor, not building control, is who to ask about any of this. On a pair like 46 and 48, High Street, speak to next door well before the scaffold goes up, because the notice period will set the start date.