01 Shared walls and notices
Under the Party Wall etc. Act 1996, notice has to come from the building owner. Notice for work to a party structure must "be served at least two months before the date on which the proposed work will begin", and section 2 lists cutting away a projecting chimney breast, jamb or flue among that work. For a new wall on or near the boundary, the notice goes out "at least one month before he intends the building work to start". A chimney shared with a neighbour's roof space is one case for the first kind of notice.
Work can start sooner "with the consent in writing of the adjoining owners and of the adjoining occupiers". Silence is not consent: after 14 days without a reply the neighbour is "deemed to have dissented from the notice", and a surveyor is appointed under section 10. Dissent opens that procedure and carries no veto. Serving the notice falls to the building owner, and the roofer does not serve it for them, so a Stapleford owner planning work to a shared wall builds the notice period into the programme from the start.