Commercial roofing: Building Regulations, CDM and asbestos

A commercial roof job meets several sets of rules at once: Building Regulations for the finished work, CDM 2015 for how it is run, and HSE's asbestos groups for what the roof is made of. Each is taken in turn here.

9 minute read

Get a written quote

Call 01582 935272WhatsApp us

Rear flat roofs of a brick shop parade with flats above
PicturedRear flat roofs of a brick shop parade with flats above.
A roof drawing with its parts named: rooflights, roller shutter, gutterRooflightsRoller shutterGutter

Several rule sets, one roof

Replacing or repairing a shop, unit or office roof is not governed by one rulebook. Different bodies set different rules, and each answers a different question: whether the finished work is sound, how the project is run, what the roof contains and how the invoice is made out. A customer who treats them as one can miss a rule entirely, so it helps to see them side by side before reading the detail. Each has its own point in the timeline: approval and permission before work, the plan before the scaffold goes up, and the assessment before any sheet is touched.

The rule sets that can touch a commercial roof job
Rule setWhat it governsWho to ask
Building RegulationsThe finished workBuilding control
PlanningPermission for changesThe council
CDM 2015How the project runsThe contractor
HSE asbestos rulesWhat the roof holdsHSE guidance
VAT reverse chargeThe invoiceAn accountant

Whether a given job needs approval, permission or notification depends on the building and the work, and the first call is to the body named in the last column. A roofer's survey shows the covering, the structure under it and the extent of the job, and those are the facts the bodies in that column ask for.

Building Regulations and who signs off

Building control is carried out by the council's building control team or by a registered building control approver. Private building control existed before 2024. What began on 6 April 2024 was the registration regime, which put private businesses doing this work onto the Building Safety Regulator's register. The completion paperwork differs between the two routes, so ask which one is being used on your project.

The Planning Portal's re-roofing test, which looks at the building envelope and the proportion of roof affected, sits in its guidance for householders. A shop, unit or office roof brings its own questions about the structure below, the covering and the energy rules. For a commercial roof the sensible question is put to building control directly: what the work involves, and whether an application is needed.

The same applies to energy efficiency. Part L is the Building Regulations topic that deals with it, and which of its tables and figures apply to a commercial building is for building control to say, not for a guess based on house guidance. Standards for materials and fixing, such as BS 5534 for slates and tiles and BS 6229:2025 for flat roofs, sit alongside the Regulations. They are codes of practice and are not themselves the law.

Planning and listed buildings

Planning permission is a separate question from Building Regulations. The householder permitted development rights for roofs, in Class C of the General Permitted Development Order, are headed "Any other alteration to the roof of a dwellinghouse", and the order does not treat a block of flats as a dwellinghouse. A shop, factory or office is outside that class altogether, so nothing in the householder rules can be assumed to cover it.

Whether a commercial re-roof or a change to its appearance needs permission is for the council to answer. The council can also say whether a conservation area or an Article 4 direction applies, since a direction takes away rights that would otherwise apply, and each council's list names the works involved. Where a roof is on a listed building, the law asks for listed building consent for works "in any manner which would affect its character as a building of special architectural or historic interest".

A new covering can change the way a building reads from the street, which is why a roof on a high street or in a conservation area deserves the question early. We check the planning or building-control route with the council before work starts, and the answer shapes the quote.

CDM 2015: client, contractor and plan

The Construction (Design and Management) Regulations 2015 apply to a commercial roof job as construction work. HSE says "A domestic client is any individual who has construction work carried out on their home, or the home of a family member, that is not done as part of any business." A shop, unit or office roof is not that, so the passing of duties in regulation 7 is not the model to rely on. Regulation 7 is written for domestic clients, and a business customer should ask the contractor what its own duties are.

Where the project has more than one contractor, regulation 7(1)(b) points to "the principal contractor for a project where there is more than one contractor". Roof work can involve several trades, such as a roofer, a scaffolder, an electrician for roof-mounted equipment and a specialist for asbestos, so the question of who is principal contractor can arise even on a small job.

A construction phase plan exists on every project, and regulation 15(5) has the contractor draw it up where there is a single contractor. The plan is the working document for the roof: how it is reached, who is on it, what is protected and how waste leaves. Ask to see it. A plan written for your roof names its own hazards, and one that could describe any roof in the country has not been written for yours.

Asbestos: HSE's three groups

HSE's rule is "If the building was built or refurbished before 2000, assume that there is asbestos in it." On an older commercial roof, cement sheeting is one material to identify, and HSE says "AC roofs are always fragile". The rule that follows depends on which group the work falls into.

HSE's groups for asbestos cement and insulating board work
GroupExample HSE gives
Non-licensedAsbestos cement roof sheeting, handled and removed with care so it does not break up
Notifiable non-licensedCement sheeting that has been substantially damaged or broken up, such as after a fire
LicensedInsulating board work where the risk assessment shows it will not be short

HSE lists "AIB white soffit panels to underside of roof eaves" among the places insulating board turns up. Waste follows its own rule: "Use a lockable skip for asbestos", because it is not good enough to throw sheeting over an ordinary skip. The household consignment-note exemption covers hazardous waste "other than asbestos waste".

Nothing here is a reason to disturb sheets to find out. The material is assessed first, the route is chosen from the group, and only then is the work priced. The page on fragile roofs and asbestos cement sheets goes through each group in turn.

Highways, wildlife and the reverse charge

Scaffolding that stands on a pavement or road needs a Highways Act 1980 scaffold licence from the highway authority. We arrange the licence with our scaffolder. Trunk roads are the responsibility of National Highways, and a roof beside one is a question for it.

Wildlife law reaches roofs as well: intentionally taking, damaging or destroying a wild bird's nest while it is in use or being built is an offence, and the same Act protects bats. GOV.UK names "repairing or replacing a roof" in its list of work that may need a Natural England licence. A survey sees any sign of nests or roosts before the work is planned.

The reverse charge on VAT for construction services applies between VAT-registered firms inside the Construction Industry Scheme, and nowhere else. HMRC's guidance says it "does not apply for supplies to end users", meaning VAT and CIS registered businesses that do not supply the work on and have told the supplier so in writing. Whether your business falls on one side or the other is for an accountant or HMRC to confirm, and the quote does not decide it. None of these three is exotic. A construction phase plan, an asbestos assessment and a VAT check are each easier to deal with before the quote than in the middle of the job, when the scaffold is up and the programme is running. Raise all three at the survey, while the scope of the job is still open.

The page on commercial roofing costs shows where these rules enter a price.

A short checklist before work starts

The rule sets above reduce to questions that can be asked of the roofer, the council and the accountant before a contract is signed. None of them is difficult, and each one avoids a surprise that is hard to undo once the scaffold is up.

  • Has building control been asked whether an application is needed, and which route is used?
  • Does the council need to be asked about planning, a conservation area, an Article 4 direction or listed status?
  • Is the roof material known, and has any asbestos position been assessed?
  • Is there a construction phase plan for this roof, and a principal contractor if several firms are involved?
  • Is the scaffold on land or on the highway, and who arranges any licence?
  • Has the VAT position been agreed with an accountant?

Nothing is priced until the roof has been surveyed. Afterwards the findings are explained in plain words, other faults included, and one written total price follows. Send a photo to WhatsApp (07880 284133) to begin; we look at what you send. Asking the questions early also makes quotes easier to compare, because a firm that has priced the answers is pricing the same job as the next. The commercial roofing hub describes the work taken on.

Questions about commercial roof rules

01Who signs off a commercial roof under Building Regulations?

Building control does, and it is carried out either by the council's building control team or by a registered building control approver. Ask which route applies and whether an application is needed for your work, because the Planning Portal's re-roofing test comes from its guidance for householders, so building control is the body to confirm a shop, unit or office roof. Putting the question to building control in writing leaves a record of the answer you were given.

02Who counts as the client under CDM 2015 on a business roof?

HSE's domestic client is an individual having work done on their home, not as part of any business, and regulation 7 passes those duties on to the contractor. A business customer is not in that position, so ask the contractor what the client's duties are on your project and who the principal contractor is if several firms are working on the roof.

03Is a construction phase plan needed on a small commercial repair?

Every project has a construction phase plan, whatever its size. For a single contractor, regulation 15(5) has the contractor draw it up. It should describe your roof: the way onto it, the protection of edges and any fragile areas, who is on the roof and the route waste takes. A plan that could describe any roof is not the one you need.

04What does HSE say about asbestos in older commercial roofs?

HSE says "If the building was built or refurbished before 2000, assume that there is asbestos in it." It also says "AC roofs are always fragile". Whole cement sheets removed with care are non-licensed work, broken-up sheeting is notifiable, and longer jobs on insulating board are licensed. The roof is assessed first, and pricing follows the survey, so nothing is quoted on a guess about the sheets.

05Does a commercial re-roof need planning permission?

The council answers that for your building. The householder rules in Class C cover alterations to the roof of a dwellinghouse, and a shop, unit or office is not one. A conservation area, an Article 4 direction or listed status can add requirements. Ask the council before work starts, and mention the covering you intend to use. On a listed building, work touching its character brings in listed building consent as well, and the council can say whether it applies.