What is a principal contractor under CDM?

CDM 2015 gives every construction project a structure of duty-holders. When a roof job brings in several firms, one of them takes the role of principal contractor.

Get a written quote

Call 01582 935272WhatsApp us

Cracked mortar under a ridge tile on a slate roof
PicturedCracked mortar under a ridge tile on a slate roof.

The short answer

Under CDM 2015, a principal contractor is the contractor appointed to manage the construction phase of a project that has two or more contractors. A project with a single contractor has no such role, because that contractor carries the duties alone.

A roof drawing with its parts named: rooflights, roller shutter, gutterRooflightsRoller shutterGutter

Who counts as the principal contractor

CDM 2015 sorts the people on a project into roles. The client commissions the work, designers shape it and contractors carry it out. A principal contractor is one contractor given extra responsibility, and the role is defined in regulation 12. It exists only when two or more contractors share a project, because that is the moment when somebody has to coordinate the rest.

A roof shows how easily that happens. A roofing firm, a scaffolding company, an electrician disconnecting rooftop wiring and a specialist for asbestos sheeting may all be on the same site, each hired separately. Every one of them is a contractor. The principal contractor is whichever of them is appointed to run the construction phase across the group, so that their work does not collide and the site stays safe for everyone on it.

When the roofer is the only firm on site, nobody holds the title. Regulation 7(1) handles that case: a domestic client's duties go to "the contractor for a project where there is only one contractor", and pass to the principal contractor where several firms are working. The title therefore measures how many firms are involved, not how large the job is.

What the role holds

The principal contractor's task is to coordinate the construction phase. In practice that can mean keeping the site organised, passing information between the firms and controlling who comes and goes. The detailed duties are set out in the Regulations and in HSE's guidance, and this page gives only the outline.

The central document is a construction phase plan. Under regulation 15, a lone contractor draws one up for its own project, and where several firms work together the principal contractor is the one who does it. The plan sets out how health and safety will be managed on the job. It can be scaled to the work, so a short repair may need a short plan and the re-roofing of a large unit a longer one covering access, edges and fragile surfaces.

Roles on a construction project
RolePart in the project
ClientCommissions the work
DesignerShapes how it is built
ContractorCarries the work out
Principal contractorRuns the construction phase across several firms

Regulation 7(1) lists the principal designer as a third option for a domestic client's duties, where there is a written agreement. That route has conditions of its own, so it is read in the Regulations rather than assumed. On a small roof repair there may be no designer involved at all, which leaves the contractor and the client as the only two roles in play.

How CDM touches a commercial roof

A business that has its own premises roofed is a commercial client, and a commercial client has duties of its own under the Regulations. They differ from the householder's, and the domestic wording does not stretch across to cover them. A building owner or facilities manager who is unsure what applies can read HSE's CDM guidance for clients before work is agreed.

Where a roofing contractor works alone, it acts as the contractor and draws up the plan itself. Where the job grows, because a scaffolding firm, an asbestos specialist or a rooflight supplier joins in, the matter of who is principal contractor arises, and it is better settled at the outset than discovered halfway through the programme. A written note of who is doing what keeps the arrangement clear for everyone on site. Agreeing the split of responsibilities in writing also helps the client, who can then see which firm to ask about site safety on any given day.

The same Regulations sit beside the rules on fragile roofs and asbestos, which the commercial roofing regulations guide brings together. The commercial roofing hub lists the other commercial pages, and pricing for roof work waits for the survey and arrives as a single written sum.

Principal contractors, questions and answers

01Is a principal contractor the same as the main roofer?

Not automatically. The role exists only where a project has several contractors, and it goes to whichever contractor is appointed to manage the construction phase. On a roofing job that may be the roofing firm, though it can equally be another firm on the site, such as the main builder. Where one contractor does all the work, there is no principal contractor at all.

02Does a small roof repair need a construction phase plan?

Every project has one, whatever its size. The plan can be scaled to the job, so a small repair may need only a short note of how access, edges and any fragile areas will be handled, while a large commercial re-roof may call for a fuller document. The contractor on a single-firm job writes it, and on a multi-firm job the principal contractor does.

03What if I am a homeowner and not a business?

HSE treats a householder who has building work done as a domestic client, and the Regulations pass that client's duties along to the contractor or the principal contractor, as set out earlier on this page. A written agreement can send them to a principal designer instead. A business, by contrast, is a commercial client, with duties of its own to read up on.

04Where can I check which duties apply to my building?

HSE publishes CDM 2015 guidance for clients, and the Regulations themselves are on legislation.gov.uk. Each project differs, so the route that applies depends on who is commissioning the work and how many contractors are involved. If you are still unsure, ring 01582 935272 with the details of the premises and ask before any work is agreed on your roof, and keep a note of the answer.