A lead-lined valley is a channel of rolled lead sheet laid along the inner corner of two meeting roof slopes. The lead sits on a timber valley board, with the covering stopping short of the centre line, so water from both slopes runs down the exposed lead and out into the gutter.
What sits in a lead-lined valley
A valley is the inward corner formed by two slopes. Rain from both pitches runs towards it, so a mistake there lets in more water than a mistake on a plain slope. A lead lining answers that by giving the water a smooth metal channel to run in, with no joints in the line of flow other than the laps between lengths.
Under the lead is a valley board or a pair of boards, fixed between the rafters to give the channel a flat base. A layer between the boards and the metal stops the lead rubbing on the timber. The lead goes down in lengths, each one overlapping the length below it, and its edges are turned up under the tiles on both sides. The tiles or slates are cut to the valley's angle and stop short of the centre, which leaves a strip of lead showing along the bottom of the angle.
Because the lead is dressed up beneath the covering on both sides, the strip that shows is narrower than the sheet. Fixings along the edges hold it down without piercing the part that carries water. The lead roofing hub sets out the other leadwork details found on a roof, and a valley is one of the busiest of them.
What each part of the valley does
From the timber upwards, a lead valley is a valley board, an underlay, the lead sheet and the tiles or slates lapping onto it, and each layer has its own job when the valley is working as built.
| Layer | Job |
|---|---|
| Valley board | A flat base between the rafters |
| Underlay | Keeps the lead off the timber |
| Lead sheet | Carries the water down the angle |
| Tiles or slates | Cut back, leaving the lead exposed along the centre |
Laps carry weight in a valley. Each length of lead must lie over the one below, so that water running down the angle is always passing from an upper length onto a lower one and never up under an edge. A lap fitted the wrong way round is invisible from the ground and leaks from the first heavy shower. Part of a valley survey is following the laps down the whole channel to the gutter or the lower roof where it ends, checking that each one is the right way round and that nothing has slipped.
The width of the lead and the length of each lap come from the specification for the job. The lead sheet codes guide explains how the thickness codes work.
Thickness, lifespan and failure
Rolled lead sheet is made to BS EN 12588 in codes 3 to 8, and code 5, for example, is 2.24 mm thick. The specification chooses the code for a given valley. MyJobQuote says that when correctly installed, lead flashing can last for over 80 years (over 100 years for higher codes) with minimal maintenance. The sentence concerns flashing, so for a valley it is a point of comparison and not a promise.
Valley lead fails in a few recognisable ways. The metal can split along the centre line, where it has moved with the weather. An edge can lift and let water run under the tiles. Debris can bank up in the channel and hold water against a lap. Where any of these has happened, a stain appears on the ceiling below the valley line, or the loft timbers beside it are damp after rain. The guide to signs of failed leadwork shows what to look for.
A blocked valley is cleared by hand from the roof, and any lead that has been dented or kinked is looked at while it is exposed. Whether a split valley is patched or relined depends on the state of the lead around it, as set out for flashings in repair or replace lead flashing.