The short answer
Re-covering your own roof is not one of the jobs the Party Wall Act lists, though work that cuts into a shared wall is. The building owner serves the party wall notice: at least two months ahead for work to a party wall, such as cutting away a chimney breast, and at least one month for a new wall on the boundary or nearby excavation.
Which jobs bring a legal notice
The Party Wall etc. Act 1996 does not mention roofing as a trade. It lists kinds of building work and gives each a notice period, and the notice is served on the adjoining owner by the building owner, meaning whoever is having the work done. The jobs near a roofing project are few, and the table sets out the periods from the Act.
| Work | Notice | Section |
|---|---|---|
| Cutting a chimney breast, jamb or flue out of a party wall | At least two months | 2 and 3 |
| A new wall built at the boundary | At least one month | 1 |
| Excavating near a neighbouring building | At least one month | 6 |
For the first row the Act requires that a party structure notice "be served at least two months before the date on which the proposed work will begin". For a new wall on the boundary, notice goes "at least one month before he intends the building work to start". Taking a breast out of a semi or a terrace is the roof-related job that lands on the first row, and the answer on Building Regulations approval for a new roof points out that approval always applies to it too.
Stripping and re-covering a roof is not among the works in that table. What brings the Act into play is a job that cuts into the shared wall, so it is worth asking at the survey whether any part of the work will do that.
What follows after a notice goes out
A neighbour who receives a notice can respond in writing. The Act allows the work to begin sooner with "the consent in writing of the adjoining owners and of the adjoining occupiers". Silence counts for something too: after the fourteen days in section 5 the neighbour is "deemed to have dissented from the notice". On this GOV.UK is direct: "You cannot assume that no response means they agree to the works."
Dissent does not end the project. Section 10 of the Act provides for a surveyor, either one agreed between both sides or one each, to settle the terms on which the work goes ahead, and GOV.UK says: "You must appoint a surveyor if you and your neighbour cannot agree." A refusal alters how the job is arranged, not whether the Act's work can proceed.
Mark the arithmetic carefully. Fourteen days is the time allowed for a reply. The two months or the one month is the gap that must be left before the work starts. For a chimney breast, then, the notice has to be served well before the date the roofers are booked, which is the reason the topic comes up when the roof is surveyed and not on the first morning on site.
Telling the neighbours anyway
Outside the Act, a word with the people next door is simple courtesy, and it pays back. A roof job brings noise, a skip, scaffold poles and workers on site, and a short note a few days beforehand, with a number to ring, can take the heat out of a complaint before it starts. That is advice for you to follow and not a legal step.
Scaffolding needs its own thought. If poles or boards have to stand on a neighbour's land or reach over it, ask for the neighbour's agreement early and get it confirmed in writing. Scaffolding on the pavement or road needs a scaffold licence from the highway authority; we arrange the licence with our scaffolder.
The roof replacement page describes the whole job. The page on how long a roof replacement takes is worth reading before you speak to the neighbours, as it explains what lengthens a job. Once the survey is done you will have the facts to share with the people next door: how large the job is, where a skip could stand and how the roof is reached. The written price is one total.