The short answer
How long a roof replacement takes depends on the roof's area and shape, the way in, the covering chosen, anything found beneath and the weather, and nobody can fix that before seeing the roof. Scaffold licences and approvals can put waiting time in front of any work on site.
Why one roof runs longer than another
Think of the job as a chain. Scaffold goes up, the old tiles or slates come off, the rafters and battens are looked over, then underlay, battens and the new covering are laid, and the ridge, verges and flashings are finished last. Each link gets longer as the roof gets bigger, and a few features lengthen it more than area does. None of them shows from the pavement.
- Area and shape: a long plain slope is quick to cover compared with a small roof broken up by valleys, hips and dormers.
- The covering itself: large concrete tiles, small clay plain tiles and natural slate are fixed differently, so each goes on at its own rate.
- The way in: a tight side alley, a sloping drive or a fence line shared with next door makes carrying materials and clearing waste slower.
- Surprises beneath: soft battens, a cracked rafter or tired lead can bring repair work once the covering is lifted.
- Additions: a chimney to re-flash, roof windows to refit or guttering tied into the same scaffold.
That is the reason a sound estimate of time arrives only with a survey of the actual roof. The quotation in writing is one total price, and the guide to what happens during a roof replacement walks through each link in the chain.
The queue in front of the first tile
Part of the elapsed time falls before anyone climbs a ladder, and it is easy to forget when a date is being pencilled in. Scaffolding on the pavement or road needs a scaffold licence from the highway authority; we arrange the licence with our scaffolder. Each authority publishes its own processing time, and three are shown below as they put it, separately.
| Council | In its words |
|---|---|
| Luton Council | "We require a minimum of 10 working days to process an application." |
| Bedford Borough Council | "Please allow 10 working days for this licence to be processed." |
| Hertfordshire County Council | "It usually takes 3 weeks to process an application." |
At any other address, ask the council responsible for the road what its present turnaround is. Hertfordshire County Council adds that a renewal application must arrive no later than five working days before the old licence runs out, so a licence already running can be extended.
Approvals form a second queue. A full re-roof needs Building Regulations approval, and the planning or building-control route is something we raise with the council ahead of any start. Where a chimney breast is being cut away on a party wall, the Act says the notice must "be served at least two months before the date on which the proposed work will begin", and the clock is the building owner's to start.
Dates, weather and the cooling-off period
Heavy rain, ice or gusts that make a pitch unsafe hold up work high on the roof, so any date is a target rather than a guarantee. The page on living in the house during the work covers the household side, and the roof replacement page describes the service from start to finish.
The contract has its own clock. An agreement signed at home after a visit follows this wording: "the cancellation period ends at the end of 14 days after the day on which the contract is entered into". Work before that date needs a written request from you. The 14 days still run and the right stays with you, though you could be asked to pay for the part already done. A different rule covers a call-out the householder asked for: "the consumer has specifically requested a visit from the trader for the purpose of carrying out urgent repairs or maintenance" removes the right.
To see what drives money as well as minutes, read the new roof costs guide. When any firm gives you a duration, ask what it rests on. An answer that names no conditions has nothing behind it.