The short answer
Building Regulations cover roof windows in two ways. A new opening cuts into the roof structure, so building control is asked before anything is cut, and a replacement unit is held to the Approved Document L figure of 1.4 W/m²K, with an energy-rating alternative. Building control confirms what the particular job needs.
Why a new opening is a structural job
Where a slope has no window yet, a new one means cutting out covering, battens and part of at least one rafter. A rafter that is cut no longer carries its share of the roof, so the framing around the hole is rebuilt to pick up that load. That structural change is the reason a brand-new opening is raised with building control before work begins.
The Planning Portal's re-roofing tests give a useful pointer. They say approval is needed when work goes past the two stated limits, and structural alterations are named among the triggers. An opening cut through a slope is a structural alteration, whatever the covering around it is made of.
| Job | What building control looks at |
|---|---|
| New opening in a slope | The structure round the opening, and the energy figure |
| Like-for-like swap | The energy figure of the new unit |
| Larger frame than before | The structure again, since rafters change |
| Rooflight on a kerb | The structure, the kerb and a separate figure |
Whether a particular swap needs an application is for building control to say. A short enquiry before the old unit comes out settles it, and costs less than finding out afterwards.
The energy figures for a unit
Approved Document L 2021 places the energy rules for replacement and new elements of a home into Table 4.2. A roof window carries a figure of 1.4 W/m²K; the alternative is a rating on the Window Energy Rating scale, where Band B minimum as the floor on that scale. A rooflight, the glazed unit "out of plane with the surface of the roof on a kerb or upstand", takes a separate and higher figure: 2.2 W/m²K.
In the 2010 Regulations a thermal element means a wall, floor or roof, and it does not include windows, doors, roof windows or roof-lights. Those units are given rows of their own, which explains why a roof's 0.15 figure is not applied to the glass in it. A renovated roof meets a different test: para 11.3 expects the whole roof element to be upgraded, where feasible, once more than 50% of its surface is renovated.
One date is worth knowing. AD L 2026 takes effect on 24 March 2027, so until then the 2021 text with its 2023 amendments stays in use. The newer edition renumbers the tables, which means a quoted figure should name the edition it came from.
Together the two Part L figures show why a quote or a datasheet that says only skylight is unclear: the name decides the row, and the row decides the figure.
Asking building control before work starts
Either the council's own team or a registered building control approver can act as building control. Registration for private approvers began on 6 April 2024, though private building control itself is older. When the work is signed off, the council's team provides a completion certificate, whereas a registered approver provides a final certificate.
Take a few facts to that conversation: the address, whether the opening is new or already there, the make and size of the unit, and the energy figure from the maker's data. Pictures of the slope and the ceiling beneath can go to WhatsApp on 07880 284133 for a look. Planning is a different set of rules, covered under planning permission for a Velux window. Having the maker's literature to hand makes the conversation quicker.
The numbers themselves get fuller treatment in what U-value a roof window needs. For the other work around a unit, the main skylights and roof windows page is the place to start. Once the survey is done, the price comes back as one written figure. Nothing in those pages replaces the council's own answer for your address.