The short answer
Overcladding a commercial roof means laying a fresh sheet system above the existing roof, which stays in place beneath it. The new layer becomes the weather surface, and the old sheets become a base. The structure has to carry the extra layer, and the question of asbestos in the old sheets comes before any decision.
What the method involves
Overcladding is a way of renewing a roof without taking the old one off. New support is fixed to the existing roof, in the form of spacer bars or brackets, and a new covering is laid on those supports. The covering can be metal sheets, an insulated panel system or a membrane over a new deck, depending on the building. The old roof is left in place as a layer beneath and keeps the building closed while the new surface goes on.
The attraction is that the building can stay in use. A roof that is stripped leaves the inside open to the weather until the new covering is on, whereas overcladding works from above and leaves the old sheets in place as a shelter throughout. It also avoids removing the old material, which matters a great deal when that material may be asbestos cement.
The method is not a repair for a roof that has failed structurally. It adds a layer, it does not cure faults beneath, and a fault left under the new covering is hidden, not mended. That is why a survey reads the old roof before overcladding is even considered, and why the choice sits beside the options on the repair or replace page.
What the structure must carry
A second layer adds load. The purlins, the rafters or trusses and the walls beneath all have to carry it, along with the wind and any snow that the new surface collects. The load of the new layer is part of the design, so the structure is checked before the new covering is specified, and a structural check can lead to strengthening or to a decision against overcladding.
Fixings are a second concern. The new supports must reach sound structure through the old sheets, and old sheets that are corroded or brittle may not hold a fixing well. The new system's fixings are calculated for the site's exposure under a site-specific fixing specification, which is drawn up for the roof in question.
| Item | Why it is checked |
|---|---|
| Structure | It must carry the added layer |
| Old sheets | They become the base |
| Fixings | They must reach sound steel or timber |
| Drainage | Gutters and outlets must still work |
The roof's edges and its drainage also change. A new layer raises the surface, so the trims at ridge, verge and eaves are renewed, and gutters may have to be altered to take the water from the higher surface. Rooflights and vents that sit in the old roof have to be raised or re-formed to meet the new surface, and each one is a joint that needs detailing.
When the old sheets are asbestos cement
Some older industrial roofs were built from asbestos cement sheets, and overcladding is sometimes proposed because it leaves them in place. HSE's guidance for older buildings is "If the building was built or refurbished before 2000, assume that there is asbestos in it." The question of what the old sheets are therefore comes first. AC roofs are always fragile, and that remains true under a new layer.
HSE separates the work by the condition of the material. Lifting asbestos cement sheets carefully and whole is non-licensed work, while cement that has broken up falls into notifiable non-licensed work. Overcladding means drilling and fixing through the old sheets, so the method has to be planned with that in mind. The asbestos cement roof page covers the risk.
Whether to overclad, or to take the old roof off, turns on the survey findings, the strength of the structure and the state of the sheets. A new covering over old asbestos cement still leaves the old material in the building, and that matters later when the building is altered or demolished. The cut-edge corrosion page is a good companion for steel roofs, and the commercial roofing hub lists more.