01 The 25 and 50 per cent tests
Not every roof job needs Building Regulations approval, and the Planning Portal draws the line with two limits. A building regulations application is not normally needed if "Less than 25 per cent of the total 'building envelope'" is affected and "Less than 50 per cent of the roof is affected". The envelope means walls, floor, roof, windows, doors, roof windows and roof-lights counted as a whole, so the first limit counts a good deal more than the roof alone, and a small roof job can fall far short of it. Check both limits against the size of the work before assuming either one is the whole test.
Stripping a whole roof and starting again goes past the 50 per cent limit, so approval is needed. The Portal's main page puts it this way: "In most situations, this work will need Building Regulations approval." For a repair, count what you can see: a patch of tiles on one slope is a small share of the whole, while a complete slope stripped to the battens is a large one.