Re-tiling and the rules

Re-tiling a pitched roof and Building Regulations

A re-tile is more than new tiles on old rafters. The Building Regulations tests come one at a time, from the Planning Portal's limits to fixing standards, Part L insulation and the certificate at the end.

9 minute read

Get a written quote

Call 01582 935272WhatsApp us

A stack of new clay plain tiles on a scaffold board
PicturedA stack of new clay plain tiles on a scaffold board.
A roof drawing with its parts named: ridge tiles, tiles, battens, underlay, raftersRidge tilesTilesBattensUnderlayRafters

Does a re-tile need an application?

Start with the Planning Portal's own sentence on re-roofing: "In most situations, this work will need Building Regulations approval." A re-tile strips a slope or the whole roof and covers it again, so it sits inside that sentence far more squarely than a repair does.

The Portal's interactive guide adds a narrow exception. No application is normally needed if the work affects "Less than 25 per cent of the total 'building envelope'" and "Less than 50 per cent of the roof is affected." Both must be met at once. The Portal's own word "normally" stays with the test, so a job near either limit is a question for the building control team before it is priced.

The envelope is the whole shell of the house, which the Portal lists as "walls, floor, roof, windows, door, roof windows and roof-lights". The roof is only one item on that list, so the first limit is hard to reach with roof work alone, and the roof limit is the one that settles a re-tile.

A re-tile of the whole roof affects more than 50 per cent of the roof, which is over the second limit. Past either limit, the Portal's guide says approval is needed, so a full re-tile is a Building Regulations job whatever the covering is. The wider pitched roofing work follows the same test, and so does the smaller end of the scale in do roof repairs need Building Regulations approval.

Where different jobs land against the limits

Jobs measured against the Portal's roof limit
JobShare of the roofWhere it lands
A few tiles replacedA small patchFar below both limits
One slope of two re-tiledAbout halfOn the line: check first
Whole roof re-tiledAll of itOver the limit: approval

The middle row is where guesses go wrong. A pitched roof with two slopes of equal size gives a half each, and the Portal's wording is "Less than 50 per cent", which leaves no room for a slope that is exactly half. Slopes can differ in size once a rear extension, a dormer or a hip is counted, so the percentage has to be worked out for the actual roof.

Percentages are not a place to be clever. For a job near a limit, the council's building control team or a registered building control approver gives the answer for that house, and the Portal's "normally" is the reason to ask.

Work to a roof that is not a dwelling's pitched roof, such as a flat garage or a commercial unit, runs on different details, and the flat-roof guides on this site cover those. For a pitched house roof being re-tiled, the issues arise in the order the job uncovers them.

A heavier covering changes the answer

The Planning Portal names another trigger, one that ignores area altogether. Approval is needed if you use a new covering material that "increases the weight of the roof covering by 15 per cent or more." Two other points count as well: a new covering whose performance in a fire is significantly different from the old one's is also caught.

Approved Document A phrases the same idea differently. It treats a roof load "increased by more than 15%" as a significant change. The Portal says 15 per cent or more and Approved Document A says more than 15%, so a page that quotes either number should name the document it comes from.

On a heavier covering, the Portal's re-roofing page says "you are advised to check with a structural engineer or surveyor before commencing with works". The rafters, purlins and walls carry whatever sits on top of them, and a heavier covering adds to what they must hold.

No direction of change is assumed. The comparison rests on data-sheet weights for the old and the new covering, per square metre, and not on an idea about which material is heavier. Even two tiles in the same material can differ in weight from one profile to another, so a like-for-like swap is worth checking as well.

You might hear

Changing tiles is a like-for-like job, so no weight check is needed.

Plain as day

A new covering 15 per cent or more heavier than the old one needs Building Regulations approval.

Fixing the tiles: BS 5534 and the end of mortar-only

BS 5534 is the British Standard code of practice that deals with slating and tiling on pitched roofs and vertical cladding, and BSI lists the 2014+A2:2018 edition as current. Marley says installing to BS 5534 "isn't required by law". The 2015 amendments, it adds, made it clear that mortar "could no longer be relied upon as the only means of securing the roof covering." The specification for a re-tile therefore sets the mechanical fixing, and mortar alone is not what holds a tile down.

Standards that bear on the fixing of a re-tiled roof
StandardWhat it coversBSI status
BS 5534:2014+A2:2018Slating and tilingCurrent
BS 8612:2018Dry-fixed ridge, hip and vergeCurrent
BS 5250:2021Moisture in buildingsCurrent, under review

Fixing is worked out for the site. Marley says the minimums in BS 5534 "will always be superseded by the generation of a Fixing Specification, which is site specific", and it wants ridge or hip tiles "mechanically fixed to resist the calculated wind uplift force." That is the standard's way of allowing for how exposed a roof is, so the number and type of fixings come from a calculation for the roof rather than a rule of thumb.

Eaves and underlay choices are part of the same specification. Ventilation is set in the pitched roof ventilation guide, and the underlay itself in what roofing underlay is.

Part L insulation when a roof is renovated

Insulation falls under Part L of the Building Regulations, headed fuel and power conservation, and Approved Document L (Volume 1, dwellings, 2021 edition) sets the figures. A renovated roof, or a retained roof above the threshold in a loft conversion, is judged on Table 4.3: the table sets a roof threshold of 0.35 W/m²K and an improved 0.16, which the document asks for where it can be done.

Paragraph 11.3 holds the trigger. It turns on whether over half of one thermal element, here the roof, is being renovated, and the upgrade then follows. Paragraph 4.13 gives a way out where the Table 4.3 figure cannot be reached for technical or functional reasons, or would not pay back within a "simple payback of 15 years or less". The roof is then taken as far as that payback allows.

Roof figures in Approved Document L, 2021 edition
SituationTableU-value, W/m²K
Retained roof, threshold4.30.35
Renovated roof, improved4.30.16

Whether a particular re-tile counts as renovation of the roof element is a question for the building control team that handles the house. AD L 2026 applies from 24 March 2027, with its tables renumbered 3.2 and 3.3, so a job that starts after that date reads the newer document and the figures are checked again then.

Who checks the work, and what certifies it

Building control is carried out by the council's building control team or by a registered building control approver. Central Bedfordshire Council, Luton Council, Bedford Borough Council, Milton Keynes City Council and Buckinghamshire Council each run their own service, and for a council route the team to ask is the one for the council that covers the house's address.

A registered approver is a private firm registered with the Building Safety Regulator. Private building control is not new: what began on 6 April 2024 is the registration regime, set up by regulations that came into force on that date, with the Building Safety Regulator holding the register.

At the end of the work, regulation 17 of the Building Regulations 2010 has the council give a completion certificate, and section 51 of the Building Act 1984 has a registered approver give a final certificate. Whichever one applies belongs with the deeds and survey reports for the house, because it records that the roof was inspected under the Regulations if anyone asks later.

The written price is a single total that follows the survey. Where a re-tile needs an application, the route is checked with the council's building control team before work starts, while that price is still being prepared, and not after the first tile is lifted.

Planning, conservation areas and listed roofs

Building Regulations and planning are two separate systems, and a re-tile is tested under both. Under the government's technical guidance, re-roofing a house is normally permitted development under Class C, which covers "other alterations to roofs such as re-roofing or the installation of roof lights/windows." The detail has its own guide, planning permission for roof work.

Class C has limits of its own, and several things can change the outcome for a particular house. An Article 4 direction can remove further permitted development rights, so we check with the council first. A listed house keeps its permitted development rights for roof work, but listed building consent is needed for anything that affects the building's character. A flat has no householder permitted development rights at all.

A conservation area does not remove Class C by itself, though it can bring an Article 4 direction with it, and it does take away the right to add dormers without an application. A re-tile in a conservation area is a question about the specific direction for that area, and the council's own list is the source for it.

None of this changes the Building Regulations questions above. A house can be exempt from planning and still need approval, or the other way round, so each test is answered on its own.

Re-tiling and the regulations, in five questions

01Does re-tiling a house need Building Regulations approval?

The Planning Portal says "In most situations, this work will need Building Regulations approval." A narrow exception exists for work affecting less than 25 per cent of the building envelope and less than 50 per cent of the roof. Putting new tiles on the whole roof affects more than 50 per cent of the roof, so it needs approval. For a job close to a limit, the building control team is the place to get a ruling.

02Does a heavier tile need an engineer's check?

A covering 15 per cent or more heavier than the old one needs Building Regulations approval, and the Portal's page says "you are advised to check with a structural engineer or surveyor before commencing with works". Approved Document A states the figure as an increase of more than 15%. The comparison uses the data-sheet weights of the two coverings, not an assumption about the material.

03Is BS 5534 a legal requirement for tile fixing?

Not as a statute: Marley points out that working to BS 5534 "isn't required by law". After the 2015 amendments, though, mortar "could no longer be relied upon as the only means of securing the roof covering." Fixings follow a site-specific fixing specification, so a re-tile quote is worked from the roof in question, and BSI lists BS 5534:2014+A2:2018 as the current edition.

04What paperwork follows a re-tile that needed approval?

On completion, a council's building control team issues a completion certificate for work that meets the Building Regulations, and a registered building control approver issues a final certificate. Keep whichever you receive with the deeds and surveys of the house. Where the covering is changed after the first application, the council or approver named on the file is the one to tell.

05Do the Part L insulation figures apply to a re-tile?

They can. Paragraph 11.3 of Approved Document L asks whether more than 50% of a thermal element's surface, here the roof, is being renovated. If so, the element is brought up to Table 4.3's 0.16 W/m²K where that is feasible and the roof sits above the 0.35 threshold. Paragraph 4.13 allows a lesser figure when the full one fails the payback test. Ask building control how it applies to your roof.